So, the project is ready, work has begun.
Since I am not a builder, but a signalman, there will be a lot of pictures and few letters in this part.
First of all, the builders threw all the excess and removed the suspended ceilings.

It has become brighter and more fun.
Then, with the crowbars removed all unnecessary, there were perennial layers of asphalt over the concrete.

')
We laid the mines of non-performing freight elevators (Interestingly, they did not hide anything in the elevator?)

Torn off old insulation

And, slowly, began to build the skeleton of the containment zone

They removed all the pipes from the future containment. We started to make the ceiling from leaks from above. We make a coupler.

The skeleton is made. The ceiling is made. The screed is flooded. It's time to sheathe

We sheathe non-combustible insulation and non-combustible moisture-proof plasterboard.

Why swear, the cashier. Everything will be well done.

She weared, sealed the gaps, painted the tight area with white paint.

We put the frame under yupsy.

Hooray raised floor brought. What is a data center without a raised floor? Is that the first category of reliability for TIA-942

With the help of a UFO-like fixture and a kettle, we assemble the raised floor. I missed the ground loop, but here we already see it.

Raised floor collected, almost ready tight area :)

At this construction was over, and miracles began with air conditioning and electricity. About this in the
third and final part of the series .