Photo report of the construction process of the data center "DataPro Tver". Part II

By September 20, the suspended ceiling, lighting of auto-rooms and technical premises on the first floor were mounted.



Car halls and technical premises on the ground floor are ready to receive equipment.
')


Built ramp for the delivery of equipment.



At the beginning of October, the premises of the second floor begin to acquire complete outlines.



A “sarcophagus” is built around the fire fighting station. Installed gas cylinders. A 100% reserve of working gas (Freon-227) was created to extinguish the fire.



Pipes from the fire extinguishing station divorced throughout the building.



Transformer substation

A concrete “cushion” has been created on the adjacent territory to house a transformer substation manufactured by Schneider Electric.



Independent bushings from the city are connected to the foundation of the substation.







The substation is placed in a block container.



In the immediate vicinity of the TP prepared site for the DGS.



The data center building is sheathed with insulating material and ceramic-granite facade tiles:





Surveillance cameras are installed around the perimeter.



In the next post, we will conduct for you a photo tour of the data center launched into commercial operation.